PUE 7, Chapter 1.8 Acceptance testing — clause by clause

PUE chapter 1.8: acceptance tests, 0.5 MΩ insulation, earthing tests.

🇷🇺 PUE — Rules for Electrical Installations (7th ed.)🕰️ PUE-6 — Rules for Electrical Installations (6th ed., 1985)🇺🇸 NEC — National Electrical Code (NFPA 70)🇪🇺 IEC 60364 / HD 60364 (EU national codes)🌎 NOM-001-SEDE, NBR 5410, AEA 90364, RETIE, NCh 4, CNE🇨🇳 GB 50054, GB 50303, JGJ 16, GB/T 16895 (IEC 60364)🇮🇳 IS 732

Document

DocumentPUE 7, Chapter 1.8 Acceptance testing
Edition2003 (ПУЭ-7, гл. 1.8)
StatusCurrent
Issued byMinistry of Energy of Russia
Applies toAcceptance testing norms for electrical installations

Document structure

№Chapter / section
1.8.1–1.8.3Scope
1.8.13–1.8.16Cable line testing
1.8.34–1.8.40Apparatus, earthing, wiring tests
PUE 7, Section 1PUE 7, Section 7PUE 7, Chapter 2PUE 7, Chapter 3PUE 7, Section 1PUE 7, Section 1PUE 7, Section 1PUE 7, Chapter 1PUE 7, Section 6 LightingSP 256PUE 7, Section 1PUE 7, Section 1PUE 7, Chapter 2PUE 7, Chapter 4PUE 7, Chapter 7PUE 7, Chapter 7GOST R 50571 Building electrical installations (Russian IEC 60364)PUE 7, Chapter 2PUE 7, Chapter 7SP 158PUE 7, Chapters 2SP 76GOST R 50571Japan: electrical rules (JIS, 100 V)

Cable lines (1.8.13–1.8.16)

Continuity, phase rotation, insulation ≥ 0.5 MΩ (LV), HV withstand for >1 kV cables.

Apparatus and earthing (1.8.34–1.8.40)

Breaker tripping, contact joints, PE continuity, earth resistance (≤ 4 Ω for TN dwellings).

Design with GorkyCAD Pro

Automatic single-line diagrams, PUE/GOST/IEC calculations, specification and PDF — from one model.

Start free

Data is for reference. Final design decisions must follow current regulations and a qualified engineer.
← Back to the country: PUE Russia: Rules for Electrical Installations · World electrical installation rules