Electrical Calculations

GorkyCAD performs all mandatory electrical calculations automatically as you design. Results update in real time — no manual recalculation needed.

Panel with circuit breakers and RCDs
Panel with circuit breakers and RCDs

Load Calculation

The Connected Load is calculated by summing the rated power of all consumers on a circuit. GorkyCAD applies demand factors according to the selected standard.

Per-circuit calculation:

  • Installed power: sum of all consumer ratings (kW)
  • Demand factor: configurable per circuit (0.5–1.0)
  • Design current: P / (√3 × U × cos φ) for three-phase

Per-phase balancing: GorkyCAD distributes single-phase loads across phases and shows the imbalance percentage. A warning appears if imbalance exceeds 15%.

Voltage Drop

Voltage drop is calculated for every circuit using the formula:

ΔU% = (ρ × L × I × 100) / (S × U)

Where:

  • ρ — conductor resistivity (copper: 0.0175 Ω·mm²/m, aluminum: 0.028 Ω·mm²/m)
  • L — one-way cable length (m)
  • I — design current (A)
  • S — conductor cross-section (mm²)
  • U — nominal voltage (230V phase, 400V line)

Limits per standard:

  • IEC 60364-5-52: 3% for lighting, 5% for other loads
  • IS 732 (India): 3% lighting, 5% power
  • IEC 60364-5-52: 3% lighting, 5% other

If voltage drop exceeds the limit, GorkyCAD highlights the circuit in red and suggests a larger cross-section.

Short-Circuit Current

GorkyCAD calculates:

  • Ik” max — maximum short-circuit current at the busbar (for breaker breaking capacity)
  • Ik min — minimum short-circuit current at the end of the line (for tripping time verification)

Calculation follows IEC 60909 / IEC 60909.

Required inputs:

  • Transformer power (kVA) and impedance voltage Uk%
  • Cable length, cross-section, and material
  • Busbar length and configuration (for 3D cabinets)

Protection Device Selectivity

For series-connected circuit breakers, GorkyCAD checks:

  • Overload selectivity — upstream breaker must not trip before downstream
  • Short-circuit selectivity — based on let-through energy I²t
  • Time-current curves — plotted for visual verification

The selectivity report shows PASS/FAIL for each pair with detailed reasoning.

Thermal Check

For distribution boards modeled in 3D:

  • Total heat dissipation of all devices (W)
  • Cabinet volume and ventilation type
  • Temperature rise °C

GorkyCAD warns if the internal temperature exceeds 40°C (IP54 enclosure) or 35°C (IP65).

Reports

All calculations are included in the Full Project PDF export:

  1. Load schedule — per-circuit and total
  2. Voltage drop table — every circuit
  3. Short-circuit currents — at busbar and endpoints
  4. Selectivity matrix
  5. Thermal report for 3D cabinets

Tips

  • Set the supply transformer parameters in Project Settings before starting
  • Verify demand factors — defaults are conservative
  • For industrial projects, enable motor starting current analysis

Frequently asked questions

Is this article free?
Yes, all articles and calculators are completely free.
Where can I run calculations?
The site offers 21 free calculators: cable sizing, breakers, RCD, voltage drop and more.
How do I prepare an electrical project?
In GorkyCAD Pro: plans, panels, calculations and a PDF set for free.
Found an error in the article?
Write to hello@gorkycad.pro — specialists will review and correct it.

Open free calculators →